Earlswood and Wood End Platform Works

Earlswood and Wood End Platform Works

Client: Network Rail

Project Value: £60k

Completion Date: July 2021

Jamieson’s were appointed by Network Rail to create a new hard standing for rail staff at Earlswood and Wood End stations.

This project was carried out under possession, using on track plant to excavate behind the coping stones and create areas of hardstanding for rail staff to walk along.

We […]

Bletchley MDU Sewer Tanks

Bletchley MDU Sewer Tanks

Client: Network Rail

Project Value: £220k

Completion Date:  May 2021

Jamieson were selected to install a new sewer treatment tank at Bletchley works Depot on behalf of Network Rail. The works were high risk due the complex temporary works to create the cofferdam and the confine space operations for working within the excavation.

The project required deep excavation of nine meter […]

Stoke NMC

Stoke NMC

Client: Network Rail

Project Completion: April 2021

Project Value: £730k

Jamieson’s were appointed to provide the design, construction, and external works at Stoke National Maintenance Centre for Network Rail.

Our works were undertaken in three phases to minimise disruption to the operational site and occupied building. We ensured all work areas were fully segregated from the general public, and operational facility and the […]

Queen’s Square Ticket Office Relocation

Queens Square Ticket Office Relocation

Client: MerseyTravel

Project Value: £175k

Completion Date:  March 2021

Jamieson’s were appointed to complete design and build for the relocation of Queens Square Ticket Office in central Liverpool.

This project required relocation of the existing ticket office to provide space for additional retail facilities. Jamieson’s undertook the full construction and fit-out of the new ticket office and  supervisors’ back office […]

Hagside Level Crossing

Hagside Level Crossing

Client: Transport for Greater Manchester

Project Value: £340k

Completion Date:  January 2021

Jamieson’s were appointed to deliver this project for Transport for Greater Manchester which involved improved access to residents across the level crossing in Radcliffe and improved sighting distances for cars and trams.

As part of our works we were required to create a new switch electrical room and electrical upgrades […]

Sale Cycle Hub

Sale Cycle Hub

Client: Transport for Greater Manchester

Project Value: £437k

Completion Date:  October 2018

Jamieson secured the works to carry out the refurbishment of a disused waiting room at Sale Metrolink Station. The station was constructed in 1849 but closed in 1991.

When the station was reopened as a Metrolink station in 1992 the waiting room was not reopened. Over the preceding years the […]

Crewe PAD Refurbishment

Crewe PAD Refurbishment

Client: Network Rail

Project Value: £300k

Completion Date:  June 2020

Undertaken on an operational sidings, Jamieson Contracting delivered an extensive internal and external refurbishment to Crewe PAD.

The current offices were out dated and Jamieson’s provided a full strip out, refurbishment and upgrade for Network Rail staff. 

Jamieson’s also managed the design and installation of a new AC and ventilation system as well […]

Emergency Covid Mortuary Facilities

Emergency Covid Mortuary Facilities

Client: TfGM/GMCA

Project Value: £515k

Completion Date: April 2020

At the height of the Covid 19 pandemic in 2020, JCL were asked by Greater Manchester Combined Authority (GMCA) to cost the creation of a temporary mortuary facility in Trafford Park. The purpose of the facility to support the hospitals in North West whose own facilities were at maximum occupancy. 

JCL were […]