Design, Refurbishment, and Installation Works at BAE Systems Barrow-in-Furness Site

Client: BAE Systems

Start Date: 2020

End Date: Various / Ongoing

Value: £ Various

Since 2020, JCL have delivered multiple schemes for BAE Systems at their high-security Barrow-in-Furness site. Projects have included the manufacture, supply, and installation of bespoke fire doors and access systems and the design and refurbishment of laboratories and stores. Following the success of our refurbishment works project in 2022, JCL […]

Kings Norton Autumn Water Tanks Renewal

Client: Network Rail

Start Date: December 2021

End Date: August 2022

Project Value: £660k

JCL were appointed by Network Rail to replace the 100,000L Water Tanks at Kings Norton Train Station. The depot is used for filling trains with water for clearing leaves off the tracks, and JCL were required to install two new water tanks double the capacity of the existing installation.

Following contract […]

Walton Summit Encapsulation Works

Walton Summit Encapsulation Works

Client: Network Rail

Project Value: £160k

Completion Date:  January 2019

Jamieson Contracting were appointed by Network Rail to complete the removal and replacement of the roof cladding on a live and operational facility.

The current roof cladding contained asbestos, requiring a stringent health and safety measures. Following its removal, Jamieson’s reclad the building with a new cladding with fire resistant insulation […]

Husco Warehouse Renovation

Husco Warehouse Renovation

Client: Husco International

Project Value: £150k

Completion Date:  February 2018

This project involved the design and build renovation of numerous warehouses on a live and operational industrial site.

Husco are an international company specialising in hydraulic and electro-mechanical controls systems. Jamieson’s were appointed to carry out different improvement works around their warehouses workshops in Runcorn.

The room comprised of numerous jobs including alterations […]