Refurbishment

TfGM Decarbonisation Scheme

Client: Transport for Greater Manchester (TfGM)

Start Date: September 2021

End Date: July 2022

Project Value: £2.8m

This project for TfGM involved working across eight sites to deliver low carbon technology upgrades in line with the GMCA’s carbon reduction programme.

The project was delivered across various transport locations in Greater Manchester, including 2 Piccadilly Place (2PP), Metrolink Queens Road Depot, Metrolink Trafford Depot, Hyde Bus […]

Design, Refurbishment, and Installation Works at BAE Systems Barrow-in-Furness Site

Client: BAE Systems

Start Date: 2020

End Date: Various / Ongoing

Value: £ Various

Since 2020, JCL have delivered multiple schemes for BAE Systems at their high-security Barrow-in-Furness site. Projects have included the manufacture, supply, and installation of bespoke fire doors and access systems and the design and refurbishment of laboratories and stores. Following the success of our refurbishment works project in 2022, JCL […]

Centre for Radiation, Chemical and Environmental Hazards (CRCE) Extension

Client: UK Health Security Agency

Project Value: £650k

Completion: July 2022

This project for the UK Health Security Agency (UKHSA) involved a single storey extension and internal alterations at CRCE Leeds, to provide new and upgraded training facilities, staff welfare areas and breakout spaces.

To allow for future expansion of the building, the works have been designed and constructed to accommodate another floor through […]

Merseytravel Tolls Extension

Client: Merseytravel

Project Value: £351k

Completion Date: June 2022

This project for Merseytravel delivered a new extension to the police and tolls building at the Wallasey/Kingsway Tunnel.

Procured through an open tender route, the scheme had complex access requirements, located adjacent to an occupied building and within close proximity to the operational tolls and a live highway.

Key to the delivery of this project was […]